Irecê I
Bahia
Solar
162 MWp
Operational Overview
Source
Solar
Capacity
133,4 MWac / 162,3 MWp
Certification
Fotovoltec – 7 years of measurements
Average Generation 35 Years
P(50): 32,6% (45,5 MWm)
P(90): 30,1% (40,2 MWm)
Transmission Line
27 km (138 kV) Transmission Line to be connected directly to the distributor’s substation
Estimated COD
May 2025
Irecê 1 has a long-term PPA in USD of 38MWm with the Mataripe refinery, belonging to Mubadala Capital, in partnership with the management company Perfin.
under construction
Irecê I
The project is located on land leased for 60 years from a single owner.
Previously, the area was a bean plantation, which implies the absence of native forest, mitigating environmental risks
Operation Phase
Works begin in March 2024. Financing in USD by BNDES.
Park Connection
The park connection is carried out directly at COELBA, thus eliminating energy generation losses up to the center of gravity (2.5%). CUSD signed in 2022, payment starts in October 2024
Park Equipment
The park will be equipped with bifacial solar modules, which benefit from the region’s soil, which is rich in limestone with excellent reflectivity, thus increasing the park’s energy production.