Irecê I

Bahia

Solar

162 MWp

Operational Overview

Source

Solar

Capacity

133,4 MWac / 162,3 MWp

Certification

Fotovoltec – 7 years of measurements

Average Generation 35 Years

P(50): 32,6% (45,5 MWm)
P(90): 30,1% (40,2 MWm)

Transmission Line

27 km (138 kV) Transmission Line to be connected directly to the distributor’s substation

Estimated COD

May 2025

Irecê 1 has a long-term PPA in USD of 38MWm with the Mataripe refinery, belonging to Mubadala Capital, in partnership with the management company Perfin.

under construction

Irecê I

The project is located on land leased for 60 years from a single owner.

Previously, the area was a bean plantation, which implies the absence of native forest, mitigating environmental risks

5

Operation Phase

Works begin in March 2024. Financing in USD by BNDES.

5

Park Connection

The park connection is carried out directly at COELBA, thus eliminating energy generation losses up to the center of gravity (2.5%). CUSD signed in 2022, payment starts in October 2024

5

Park Equipment

The park will be equipped with bifacial solar modules, which benefit from the region’s soil, which is rich in limestone with excellent reflectivity, thus increasing the park’s energy production.