Complexo Solar Irecê – Phase 2
João Dourado - Bahia
Solar
193,6 MWp
Operational Overview
Source
Solar
Capacity
193,6 MWp / 161 MWac
Certification
Fotovoltec – 7 years of measurements
Average Generation 35 Years
P(50) 33.4% (51.9MWm)
P(90): 31.0% (49.0 MWm)
Transmission Line
27 km (230 kV)
Estimated COD
July 2027
SPE 1
UFV Solar Irecê 1 – 69 MWac – AUTHORIZATION RESOLUTION No. 11,462, OF APRIL 5, 2022
SPE 4
UFV Solar Irecê 4 – 46 MWac – AUTHORIZATION RESOLUTION No. 11,464, OF APRIL 5, 2022
SPE 5
UFV Solar Irecê 5 – 46 MWac – AUTHORIZATION RESOLUTION No. 11,465, OF APRIL 5, 2022
Ombudsman Channel – Implementation Phase
Use this channel for suggestions, questions, or complaints about the project’s implementation work.
(74) 99946-2004
solarirece2@illian.com.br
Environmental licensing
Consult the project’s environmental licenses
Under construction
Complexo Solar Irecê – Phase 2
It is located adjacent to the Irece 1 project (under construction) on land leased from a single owner.
Previously, the area was a bean plantation, which implies the absence of native forest, mitigating environmental risks
Project Phase
Construction of the construction site
Park Connection
The Irecê II connection will be carried out at the Irecê Substation, at 230kv and already has an Access Opinion and CUST signed.
Park Equipment
Both parks will be equipped with bifacial solar modules, which benefit from the region’s soil, which is rich in limestone with excellent reflectivity, thus increasing the energy production (capacity factor) of the parks.